Galter Pavilion Bridge Northwestern Memorial Hospital

An “out of the box” erection plan was called for on this new 9th-floor bridge connecting two campus buildings. A 30-ton crane was hoisted to the existing 8th floor and used to erect the steel and curtainwall. This method allowed for both hospital wings to remain operational throughout construction.